Anexo M - Cronograma Físico-Financeiro
|
Item |
Descrição |
Total Por Etapa |
30 DIAS |
60 DIAS |
90 DIAS |
120 DIAS |
150 DIAS |
180 DIAS |
210 DIAS |
240 DIAS |
270 DIAS |
|
1
|
SERVIÇOS PRELIMINARES
|
100,00% |
25,79% |
|
12,80% |
21,19% |
|
5,18% |
5,18% |
12,26% |
17,60% |
|
68.026,86 |
17.547,01 |
|
8.708,67 |
14.417,95 |
|
3.521,42 |
3.521,42 |
8.340,03 |
11970,36 |
||
|
2
|
ALVENARIA/VEDAÇÃO/DIVISÓRIA
|
100,00% |
|
|
100,00% |
|
|
|
|
|
|
|
2.144,85 |
|
|
2.144,85 |
|
|
|
|
|
|
||
|
3
|
INSTALAÇÕES HIDROSSANITÁRIAS
|
100,00% |
|
34,45% |
5,78% |
|
3,91% |
|
33,39% |
3,68% |
18,79% |
|
33.056,57 |
|
11.387,64 |
1.909,99 |
|
1.294,05 |
|
11.036,09 |
1.217,36 |
6.211,44 |
||
|
4
|
PISOS
|
100,00% |
|
25,81% |
5,08% |
|
20,64% |
20,64% |
12,01% |
8,04% |
7,79% |
|
73.034,36 |
|
18.846,62 |
3.710,30 |
|
15.075,15 |
15.075,15 |
8.769,46 |
5.869,02 |
5.688,66 |
||
|
5
|
PINTURA
|
100,00% |
|
24,66% |
7,39% |
|
16,92% |
16,92% |
15,21% |
13,22% |
5,67% |
|
32.021,17 |
|
7.895,05 |
2.365,36 |
|
5.419,42 |
5.419,42 |
4.872,01 |
4.232,75 |
1.817,16 |
||
|
6
|
REVESTIMENTOS
|
100,00% |
21,82% |
|
12,17% |
15,14% |
15,14% |
15,27% |
|
18,82% |
1,64% |
|
5.091,21 |
1.110,96 |
|
619,61 |
770,73 |
770,73 |
777,66 |
|
958,2 |
83,32 |
||
|
7
|
IMPERMEABILIZAÇÃO
|
100,00% |
24,87% |
|
6,18% |
9,59% |
28,78% |
3,23% |
9,70% |
10,04% |
7,59% |
|
289.103,88 |
71.908,65 |
|
17.870,62 |
27.738,00 |
83.214,00 |
9.351,16 |
28.053,49 |
29.012,46 |
21.955,50 |
||
|
8
|
LIMPEZA E ENTREGA DA OBRA
|
100,00% |
34,09% |
3,79% |
5,28% |
26,17% |
|
9,78% |
6,87% |
6,31% |
7,72% |
|
21.986,32 |
7.495,69 |
832,85 |
1.161,12 |
5.752,95 |
|
2.149,50 |
1.510,29 |
1.387,42 |
1.696,50 |
||
|
9
|
ADMINISTRAÇÃO LOCAL
|
100,00% |
11,32% |
11,32% |
12,48% |
11,32% |
11,32% |
10,77% |
7,67% |
11,32% |
12,48% |
|
129.576,20 |
14.668,03 |
14.668,03 |
16.171,10 |
14.668,03 |
14.668,03 |
13.955,36 |
9.938,49 |
14.668,03 |
16.171,10 |
||
|
Porcentagem |
|
|
|
|
|
|
|
|
|
|
|
|
Custo |
|
112.730,34 |
53.630,19 |
54.661,62 |
63.347,66 |
120.441,38 |
50.249,67 |
67.701,25 |
65.685,27 |
65.594,04 |
|
|
Porcentagem Acumulado |
|
|
|
|
|
|
|
|
|
|
|
|
Custo Acumulado |
|
112.730,34 |
166.360,53 |
221.022,15 |
284.369,81 |
404.811,19 |
455.060,86 |
522.762,11 |
588.447,38 |
654.041,42 |
|